集通铁路长大隧道GSM-R冗余方案研究

周 伟   

  1. 中铁电气化局集团有限公司设计研究院,北京 100166
  • 收稿日期:2020-10-23 修回日期:2021-01-18 出版日期:2021-03-25 发布日期:2021-08-17

Research on GSM-R Redundancy Plans for Long Tunnels of Jining-Tongliao Railway

Zhou Wei   

  1. Design & Research Institute, China Railway Electrification Engineering Group Co., Ltd., Beijing 100166, China
  • Received:2020-10-23 Revised:2021-01-18 Online:2021-03-25 Published:2021-08-17

摘要: 针对集通铁路的长大隧道,论述分布式基站和数字光纤直放站的两种冗余方案,通过分析比较两种方案的单网交织以及同站址双网冗余覆盖方式,推荐采用分布式基站单网交织冗余方案。

关键词: 长大隧道, 分布式基站, 数字光纤直放站, 单网交织, 同站址双网

Abstract: This paper discusses two redundancy plans of distributed base stations and digital optical-fiber repeater stations for the long tunnels of Jining-Tongliao Railway. The single-network interleaving redundancy plan for distributed base stations is recommended after analyzing and comparing single-network interleaving and double networks for the same site respectively for both redundancy plans.

Key words: long tunnels, distributed base stations, digital optical-fiber repeater stations, single-network interleaving, double networks for the same site

中图分类号: