Application of Turnout Test Simulation Conditions in Commissioning Construction of Signaling Engineering

Xu Bin   

  1. Xuzhou Signaling & Communication Depot, China Railway Shanghai Group Co., Ltd., Xuzhou    221000, China
  • Received:2020-07-13 Revised:2021-02-18 Online:2021-08-25 Published:2021-08-25

道岔试验模拟条件在信号工程开通施工中的应用

许 宾   

  1. 中国铁路上海局集团有限公司徐州电务段,江苏徐州 221000

Abstract: This paper discusses the necessity of adding test simulation conditions during the commissioning construction of signaling engineering, and discusses in detail how to define the equipment for using test simulation conditions, and how to make and add test simulation conditions. It also compares the advantages and disadvantages of using test simulation conditions from the distribution board and assembly rack, and analyzes the board control measures in the process of using test simulation conditions. In the commissioning construction of signaling engineering such as station/yard reconstruction and renovation, the method of adding test simulation conditions is adopted to conduct interlocking test, the real control and use of test simulation conditions, so that it becomes the condition line of interlocking test and the "auxiliary line" of construction safety to ensure the construction progress and operation safety.

Key words: commissioning construction, interlocking test, simulation conditions, application analysis

摘要: 论述信号工程开通施工过程中加装试验模拟条件的必要性,探讨如何界定使用试验模拟条件的设备以及试验模拟条件的制作、加装方法,比较从分线盘处、组合架处分类使用试验模拟条件的优缺点,解析试验模拟条件过程中的卡控措施。在站场改造、更新改造等信号工程开通施工中,采取加装试验模拟条件的方法进行联锁试验,真正的管好、用好试验模拟条件,使其成为联锁试验的条件线,成为施工安全的“辅助线”,达到确保施工进度和行车安全的目标。

关键词: 开通施工, 联锁试验, 模拟条件, 应用分析

CLC Number: