Discussion on Simulation Test of Train Control Center

Wang Meng   

  1. Beijing Railway Signal Co., Ltd., Beijing    102613, China
  • Received:2020-08-25 Revised:2020-09-17 Online:2021-01-25 Published:2021-01-25

简谈列控中心仿真验收测试

王 猛   

  1. 北京铁路信号有限公司,北京 102613

Abstract: The high-speed railway takes the train control center (later referred to as TCC) as the center. Adaptive design of the functions is performed through TCC software to realize its huge computation processing function combined with site infrastructure construction. Therefore, before the opening of a new line, in order to ensure the operation safety of high-speed trains and improve transport efficiency, it is necessary to carry out traversal test on the functions and logic relationship of TCC software, that is, TCC software simulation test. The TCC software tested by the simulation platform can greatly reduce the probability of on-site problems. This paper introduces the key issues such as TCC simulation test platform modeling, environment construction, data configuration, test flow, problem feedback and test record, hoping to provide reference for the commissioning and putting into service of the TCC product software of newly-built high-speed railway line.

Key words: high-speed railway, simulation test, TCC, test flow

摘要: 高速铁路列控中心(简称TCC)为中枢,通过TCC软件将其功能进行适应性设计,结合现场基础工程建设实现其庞大的运算处理功能。新建线路开通前,为确保高铁列车运营安全,提高运输效率,需要对TCC软件的功能及逻辑关系进行遍历测试,即TCC软件仿真测试。通过仿真平台测试合格软件,可大大降低高铁现场出现问题的概率。从TCC仿真测试平台建模、环境搭建、数据配置、测试流程、问题反馈、测试记录等重点关注的问题展开介绍,为新建高铁线路列控中心产品软件的调试与开通提供参考和借鉴。

关键词: 高速铁路, 仿真测试, 列控中心, 测试流程