DCS Wired Network Transition Plan of Urban Rail Transit Signaling System

Ma Long   

  1. Beijing Urban Construction Design & Development Group Co., Ltd., Beijing    100037, China
  • Received:2019-11-26 Revised:2020-12-29 Online:2021-08-25 Published:2021-08-25

城市轨道交通信号系统DCS有线网络过渡方案研究

马 龙   

  1. 北京城建设计发展集团股份有限公司,北京 100037

Abstract: According to the requirement of setting up temporary OCC in the Zhengzhou urban rail transit line 14 project phase 1, this paper puts forward a transitional scheme of DCS wired network based on the original design scheme of signaling system of DCS wired network, and discusses and studies the concrete implementation process of the scheme and its later relocation to the second dispatching center.

Key words: Zhengzhou urban rail transit line 14 phase 1, DCS wired network transition plan, temporary OCC

摘要: 结合郑州市轨道交通14号线一期工程需设置临时控制中心的需求,在信号系统DCS有线网络原设计方案的基础上,提出DCS有线网络过渡方案,并对该方案具体实施过程和后期改迁至第二调度中心进行探讨与研究。

关键词: 郑州市轨道交通14号线一期, DCS有线网络过渡方案, 临时控制中心

CLC Number: